On June 4th the San Bernardino City Council approved a $6.25 million street paving project that will repair and upgrade 14 streets across the City.
The project will be funded with the annual Road Maintenance and Rehabilitation Program (RMRA/SB1) and gas tax funds. Work on the nearly seven miles of roads will be performed by the Matich Corporation.
The project includes the following locations:
-
- North Mayfield Avenue from West 8th Street to 10th Street
- North Western Avenue from 8th Street to Union Street
- East Gilbert Street from North Waterman Avenue to Canyon Road (to the
- Bridge)
- West 14th Street from North G Street to North E Street
- East Hardt Street from South Tippecanoe Avenue to Richardson Street
- East Holden Drive from the West End to the East End
- North Orange Street from 210 FWY to Highland Avenue
- North Electric Avenue from West 40th Street to 48th Street
- North Varsity Avenue from West College Avenue to Universal Ave
- West College Avenue from University Parkway to North Citadel Avenue
- West Roosevelt Avenue, from Macy Street to University Parkway
- North Macy Street from Roosevelt Avenue to West and East end of West
- Washington Avenue (including Lincoln Avenue from West End to University
- Parkway)
- West 34th Street from North Mountain View Avenue to North Sierra Way
- North Mountain View Avenue from West 30th Street to Edgerton Drive
Work will begin later this summer and is expected to be completed in the spring of 2026.