The San Bernardino City Council continues to make progress on its plan to repave and resurface 53 streets and repair sidewalks throughout the City.
The Council approved the third-phase of the plan earlier this month, awarding a $6.4 million contract to the Matich Corporation. The third-phase will include segments of fourteen streets and ADA accessible ramps, drainage, sidewalk installation, signage, and curb/gutter improvements.
“This is another example of San Bernardino continuing to upgrade our city’s infrastructure,” said City Manager Robert D. Field. “There is a lot more work to do, but our residents are already noticing a difference.”
In 2020 the Public Works Department conducted a pavement management analysis to prioritize the streets in most need of rehabilitation.
Streets to be improved in phase-three are:
- Temple Street – from J Street to Perris Street (Ward 1)
- Acacia Street – from 10th Street to Baseline Street (Ward 2)
- Prospect Avenue – from Congress Street to Flood Control (Ward 3)
- Ralston Avenue – from Mt. View to Waterman Avenue (Ward 4)
- Dover Drive – from Mountain Drive to I Street (Ward 5)
- Meridian Avenue – from Foothill Blvd. to 7th Street (Ward 6)
- Parkside Avenue – from 30th Street to Parkdale Avenue (Ward 7)
- Congress Street – from Mt. Vernon to K Street (Ward 3)
- Virginia Street – from E Street to F Street and G Street to H Street (Ward 2)
- Niles Street – from San Gabriel Street to Crestview Street (Ward 2)
- Trenton Street – from Crestview Avenue to Valencia Avenue (Ward 2)
- Cedar Street – from Highland Avenue to 29th Street (Ward 2)
- Arden Street – from Highland Avenue to Pacific Street (Wards 2,7)
- Country Club Lane – from Waterman Avenue to Fremontia Drive (Ward 7)
Work on the third-phase will begin in early May and should be completed by October 2022.